MOE Level 3 & 4 Fitout

Client:
Ministry of Education

Location:
Pukaki Street, Rotorua

Year Started:
2013

Duration:
2.5 Months

Project Value:
$950,000

Contract Type:
Lump Sum

A staged two level internal fit-out, this project involved working on levels 3 and 4 of an existing building while the lower levels were fully tenanted.

Work commenced on level 4 on 10 June 2013 with demolition of the existing internal walls and partitions. New walls were built to match the new layout and services were upgraded. New carpet tiles were laid, the area was fully re-painted and a new reception area with feature wall was installed opposite the lift. Level 4 was handed over on time on 22 August 2013. This level is occupied by the Ministry of Education.

Demolition on level 3 commenced in September 2013 and the entire level was stripped out. New partition walls were built and some services were up graded. A staff kitchen area was created and a new reception area was installed opposite the lift. New floor coverings were installed throughout. This level is occupied jointly by the Ministry of Education and the Inland Revenue Department.

On the ground floor of the building a secure storage area was also built.
The project was completed at the end of October 2013.