BMW Showroom Extension

Client:
Dilworth Trust Board

Location:
Newmarket, Auckland

Year Started:
2005

Duration:
7 Months

Project Value:
$2.6M

Contract Type:
Tender

Canam Interiors were appointed to refurbish and extend the existing Team McMillan Showroom and refurbish the BMW Lifestyle and Parts areas.

The works comprised of demolition of the existing Showroom, Lifestyle and Parts areas, extending the existing structure to provide additional floor area in the Showroom, and the reconfiguration of the Lifestyle and Parts area.

An extensive area of the existing roof was replaced, partly over the service workshop which remained operational during these works.

As part of the redevelopment, a new electrical transformer was also installed. Internally high class, internal finishes were matched externally with Aluminum shop fronts and Alucobord cladding, together with forecourt paving and external lighting which set the building apart after dusk.